Updated 9 November 2026 · 2 min read

Lead time is part of both the reorder point and the safety stock. Many webshops use the figure the supplier has stated, but the actual lead time is often longer, and it varies. Both can be measured from the orders already received.

Measure from order to receipt

The lead time is the time from when the order is sent to the supplier until the goods are received and can be sold. That is the time the stock has to last. The supplier’s lead time often only covers dispatch, which leaves out freight and receiving.

A supplier has delivered five orders in 52, 58, 61, 55 and 74 days. The average is:

(52 + 58 + 61 + 55 + 74) / 5 = 60 days

If the supplier has stated 45 days and you plan with that, you order 15 days too late every time.

Measure the variation

The variation is the standard deviation of the measured lead times. For the five orders, the deviations from the average are −8, −2, 1, −5 and 14 days:

√((64 + 4 + 1 + 25 + 196) / 4) = √72.5 = 8.5 days

You divide by 4 and not 5 because it is a sample. With fewer than three orders the figure is too uncertain to use.

What the variation means for safety stock

A product sells 2.6 units a day with a variation of 1.8 units, and the service level is 95%. Using the formula from the guide to safety stock and a lead time of 60 days:

Safety stock
Fixed lead time 23 units
Variation of 8.5 days 43 units

The variation in lead time nearly doubles the safety stock for that product. It is often a better place to act than raising the service level: a supplier that delivers more consistently saves stock on every product.

Pitfalls

  • Partial deliveries. If an order arrives in two parts, measure to the last part, or measure per line if possible.
  • Holidays. Chinese New Year and the supplier’s summer holiday can add several weeks. It is probably better to enter them as a period than to let them raise the average all year.
  • Old orders. If the supplier has changed shipping method or warehouse, orders from two years ago say little. Use the most recent orders.
  • Orders that were never registered as received. They should not be included in the measurement.

Measured lead time in lesslater

If a supplier has at least three received purchase orders, lesslater uses the measured lead time from order to receipt instead of the entered one, and the variation is added to the safety stock. A lead time set on an individual product still takes precedence. Orders that are late compared with the expected date are shown on the purchase orders with the number of days.