The reorder point is the stock level at which you need to order to get the product in before it runs out. When stock reaches the point, it is time to order.
The formula
Reorder point = sales during lead time + safety stock
If a product sells 2.6 units a day and the lead time is 56 days, about 146 units are sold while you wait. With a safety stock of 23 units, the reorder point is 169 units.
With 180 units in stock, there are therefore about four days until the product has to be ordered. It is a good example of why long lead times are hard to manage by gut feeling: the stock looks large, but it has to last longer than you think.
Use available stock
The stock you compare with should be the available stock:
Available = in stock + incoming goods − reserved for orders
If you forget incoming goods, you order the same thing twice. This happens especially when several people order from the same supplier, or when an order has been sent but not yet registered.
Seasonality moves the point
The formula above uses a fixed sales rate per day. If you are ordering in October for a product with a 56-day lead time, it is the sales in November and December that count, and they can be twice as high as October’s. You then have to sum the forecast for the actual days in the lead time instead of multiplying an average by the number of days.
If you do not, Christmas products typically arrive too late, and after Christmas you order too much, because December still pulls the average up.
Reorder point or fixed order day
Many webshops order from a supplier on a fixed day, e.g. every other week. The reorder point then also has to cover the time until the next order day:
Sales during (lead time + days until next order) + safety stock
Otherwise stock may drop below the point the day after you ordered, and the product then has to wait a whole cycle.
What about the quantity
The reorder point says when. How much to order depends on the order cycle, minimum order, case size and price discounts. This is described in the guide to order quantity.
Order dates in lesslater
lesslater calculates the order date for each product from the day-by-day forecast during the lead time, incoming goods and safety stock. The suggestion is either “order now”, “order later” with a date, or nothing, and the order calendar shows what needs to be ordered week by week.